INTERACTIVE 3D VIRTUAL FACILITY (CLICK HARDWARE TO PROBE)
TIME: 0.0s
๐ 2026 AI FACTORY:
120.0 kW/RACK (GB200 NVL72)
88% LIQUID DTC / 12% AIR
TCS: 140.0 GPM (ฮT 15.0ยฐC PG25)
TOKENS: 184,200 /s
PUE: 1.118
๐ฌ FLUKE-DC900 PROBE
TARGET: NONE
SELECT ANY HARDWARE COMPONENT IN 3D TO MEASURE VOLTAGE, CURRENT, POWER, AND AIRFLOW.
Thermal Envelope:
≤20ยฐC Cool
20-24ยฐC Nominal
24-27ยฐC Warn
>27ยฐC Alarm
๐๏ธ 42U RACK DESIGNER STUDIO & DEEP HARDWARE VISUALIZER
CABINET:
โก PDU-A (PRI)
0.0 kW
0.0 A
NEC ≤24A (30A Max)
โก PDU-B (RED)
0.0 kW
0.0 A
NEC ≤24A (30A Max)
HARDWARE INSPECTOR
U-Slot Position:
U--
Component Type:
--
AC Electrical Draw:
-- W
Cooling Airflow:
-- CFM
Inlet → Exhaust Temp:
--ยฐC → --ยฐC
Silicon Die Junction:
--ยฐC
Throttling Status:
NOMINAL
PDU Feed Branch:
--
Assigned Receptacle:
--
Cables Connected:
--
๐ง REAR LIQUID MANIFOLD
VALVE: OPEN (FLOWING)
๐ฅ๏ธ 3D RACK ISOMETRIC SCAN
1075mm Depth โข 2.0mm Rails
๐ก WHAT DOES THIS PART DO?
Select any component in the 42U rack rail (ToR switch, patch panel, KVM, compute server, AI GPU node, storage, or UPS) to see real-life engineering guidelines and standards.
STANDARDS: ASHRAE TC 9.9 โข TIA-942 โข IEEE 802.3 โข NEC ARTICLE 645
๐ ARCHITECTURAL FACILITY BLUEPRINT & MULTI-ZONE MAPPING
TIER III โข 420 mยฒ โข 8 FACILITY ZONES
SIMULATION LAB SANDBOX (POWER GRID, SUBSTATION, COOLING PLANT & TOPOLOGY)
โก UTILITY POWER GRID & SUBSTATION (13.8 kV) GRID: ENERGIZED
Manage commercial utility grid feed (13.8 kV), pad-mount step-down transformers (13.8kV → 480V), and overhead power busways.
Commercial Grid Master Breaker
13.8 kV Feeder โข 60 Hz โข ATS Primed
PAD-MOUNT STEP-DOWN TRANSFORMERS
OVERHEAD TRACK BUSWAYS (800A DUAL PATH)
๐ง CENTRAL COOLING PLANT & TES STORAGE CHWS: 7.0ยฐC
Direct-drive centrifugal chillers, outdoor induced-draft cooling towers, and 3 cylindrical Thermal Energy Storage (TES) chilled water tanks.
WATER-COOLED CHILLERS (CENTRIFUGAL)
INDUCED-DRAFT COOLING TOWERS
Thermal Energy Storage (TES) 3-Tank Buffer
450,000 L โข 3,138 kWh Reserve
SoC: 100.0%
Ride-Through Autonomy: 360.0 mins
๐ FACILITY UPS & BATTERY CONFIGURATOR
Configure double-conversion UPS rating, battery storage capacity, and operating topology per ANSI/ASHRAE Standard 90.4-2022.
ECO Static Bypass Mode
Boosts efficiency from 95.8% to 99.1%
Calculated Runtime: 18.4 mins
Estimated Autonomy at Full Load: 14.2 mins
โก BRANCH CIRCUIT BREAKERS & PHASE BALANCER (UGLY'S)
208V Line-to-Line 2-pole 30A circuit breakers. Continuous duty is capped at 80% (24A) per NEC Article 645.
RACK FLEET MANAGER (POWER & WORKLOAD DIRECT CONTROLS)
ELECTRICAL POWER SINGLE-LINE DIAGRAM (480V 3-PHASE & UPS)
PUE: 1.185
2D NAVIER-STOKES EULERIAN CFD DIGITAL TWIN (JOS STAM STABLE FLUIDS)
โข ∇•u = 0 • BOUSSINESQ THERMAL BUOYANCY
TIME: 0.0s
RENDER:
18ยฐC
38ยฐC+
๐โก ELECTRICITY & HYDRONIC PHYSICAL FLOW VISUALIZER
โข FIRST LAW & DUAL-DOMAIN LOGIC
โก FIRST LAW: 0.00 kW DRIFT
๐ง MASS: 0.00 LPM DRIFT
โก ELECTRICAL DISTRIBUTION & KIRCHHOFF FLOW NETWORK
GRID: 120.4 kW
๐ง HYDRONIC COOLING & THERMODYNAMIC FLOW NETWORK
PLANT: 1200 LPM
โก
UTILITY POWER GRID FEED (13.8 kV Delta)
TIER III / 2N REDUNDANT
Click any node in the SVG diagrams above or choose a drill preset to inspect governing formulas, standards, and live telemetry.
โ๏ธ REAL-WORLD OPERATION & PHYSICS
The commercial utility feed delivers bulk alternating current at medium voltage (13.8 kV) via underground duct banks.
P = √3 × V_LL × I_L × cos(θ)
๐ GOVERNING CODES & STANDARDS
โข IEEE 493 (Gold Book): Reliable power design.
โข NEC Article 645 & 708: Critical operations power systems.
โข ANSI/ASHRAE 90.4: Electrical Loss Component (ELC) ≤ 0.125.
โข NEC Article 645 & 708: Critical operations power systems.
โข ANSI/ASHRAE 90.4: Electrical Loss Component (ELC) ≤ 0.125.
COMPLIANT: IEEE Std 446 Emergency Standby
โ ๏ธ FAILURE CASCADES & LIVE TELEMETRY
Utility loss transfers load seamlessly to UPS battery float inverter while triggering diesel ATS auto-start.
V: 13,800 V
Freq: 60.00 Hz
P: 120.4 kW
Status: ONLINE
๐ GOVERNING FIRST-PRINCIPLES PHYSICAL FORMULAS & CONTINUOUS LOGIC
STRICT FIRST LAW ENERGY & MASS CONSERVATION VERIFIED
1. First Law of Thermodynamics
Σ P_in ≡ Σ P_out + Σ P_losses
P_grid (120.4 kW) = P_IT (80.4 kW) + P_cool (28.2 kW) + P_loss (11.8 kW) • Error: 0.00 kW
2. Kays & London ε-NTU Heat Exchanger
ε = Q_actual / [C_min • (T_h,in - T_c,in)]
ε = 86.4% • Q_cdu = 28.5 kW • FWS: 12.0°C → 18.5°C • TCS: 30.0°C
3. Darcy-Weisbach Head Loss & Cold Plates
ΔP = f • (L/D) • (ρ v² / 2)
Head Loss = 4.2 PSI • T_j = T_coolant + ψ_ca • P_socket • Die Junction: 62.4°C
4. Ugly's 3-Phase Vector Sum & Harmonics
I_N = √(I_A² + I_B² + I_C² - Σ I_i I_j) + I_triplen
I_A=154.5A, I_B=158.4A, I_C=158.4A • I_N=18.2A • THD-i=4.2%